Summary duration % Complete

A
Ahmed KHR 👤 Member for 15 years 6 months

Dear Planners;

I'm worried about the Duration % complete on summary tasks on MS Project programme calculation!

 

So, Any body have an Idea about please share it.

 

Regards.

 

A
ali deveboynu 👤 Member for 16 years 2 months

% complete on summary task are calculated by simple aritmetic average , assume you have 2 task under summary task , which has 10 and 20 days durations and %40 and %50 completes , % complete calculates such as (40*10)+(50*20)/30

best regards