Update Process

Hi:

What is the use of Update Process (Tools-> Process Update). When it is used. And what is difference between Appling actuals and Update Process?

Asim

G
Gary Whitehead 👤 Member for 17 years 2 months

It's Update Progress, not update process.

 

Usibng the update progress tool allows you to quickly progress multiple tasks on the asumption that everything happened as planned. ie if the early start and/or early finish of an activity is before the new data date, that will become it's actual start and/or actual finish.

 

Applying actuals allows you to tell Primavera when things actually happened, rather than when they hsould have happened.

 

In 95% of cases, I feel the update progress tool to be a tool for the lazy planner.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts