Thanks Mike

This makes things clearer.

Also Chris i got the AACEI document  you suggested above, tough read but worth it.

Thnanks agin for the tips.

 

Aidan

Member for

19 years 10 months

Hi Aidan

The usual method is to insert a dumkmy activity that represents the duration of the delay event and link it to the affected task(s).

The delay event duration is from the day the event first raised its head to the earliest date that the affected task could have started.

Best regards

Mike Testro

Member for

14 years 6 months

Hi Amit

 

An example of the delays would be underground obstructions not known at tender and that did not show up during pre-excavation scanning. These obstructions subsequently required halting excavation then supporting the pipe/cable etc and this delayed the entire trenching process.

 

The client is not accepting that we did not know about the obstructions but their tender drawings did not show them.

Aidan

Member for

14 years 6 months

Thanks Chris

 

I'll check into these.

 

Aidan

Member for

20 years 9 months

Aidan

There are two very good references you should examine, the first is by the society of construction law in the UK.  http://www.eotprotocol.com/ and the Association for the Advancement of Cost Engineering.

 Recommended Practice No. 29R-03 Forensic Schedule Analysis;

 

Neither are an easy read but well worth the effort.

 

Hope this helps

 

 

Chris

Member for

20 years 9 months

Aidan

There are two very good references you should examine, the first is by the society of construction law in the UK.  http://www.eotprotocol.com/ and the Association for the Advancement of Cost Engineering.

 Recommended Practice No. 29R-03 Forensic Schedule Analysis;

 

Neither are an easy read but well worth the effort.

 

Hope this helps

 

 

Chris

Member for

14 years

Hi Aidan,

           The impacted delay causes how to reperesent in programme???Can you post any sample,please?????

 

Regards

Amit Kumar

Member for

16 years 11 months

Hi  Aidan Kelly

The methods may vary but the concept is to determine the potential delay event/ fragnet which justified duration associated with it and it has to be impacted on the reference program used for claim presentation

Cheer's

Shahul