Contract Price

R
Razi Khan 👤 Member for 21 years 11 months
D
Dinesh Kumar Damavarapu 👤 Member for 24 years 3 months

Hi Khan,



The total Contract sum/Contract sum is inclusive of provisional sums and day works and the effective contract sum is exclusive of provisional sums and day works.



Regards



Dinesh