Urgent Repsonse

Hi all ,

 

I just created a Baseline , submitted to my client ... which he did replied with comment ... One of the comment sounds confusing to me.. SAT which order wise is know as Materials delivery at site was place under the Procuremnt WBS in my Schdule , But my Client feels otherwise ...

Please find below the comments

* Why is SAT ( Site Acceptanc Test ) a sub heading under Procuremnet WBS , SAT should be shown under construction Phrase *

 

You accelerated Responds will be of great Important ... 

M
Mike Testro 👤 Member for 20 years 6 months

Hi Ayeni

Provided your logic is sound it doesn't matter where you put the SAT.

If you are doing a test pile for instance that should be in the construction phase.

Just move it and keep the man happy.

Best regards

Mike Testro.

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts