How do you do the following things in P6

R
Raul Santos 👤 Member for 16 years 7 months

1. How do you create a project?

2. Once you have developed your schedule, how do you baseline it?

G
Gary Whitehead 👤 Member for 17 years 2 months

1. Got to the "File" menu, and left-click on "New"...

2) Go to "project" menu > "Maintain Baselines" > add

then go to "project" > "assign baselines", and confirm the correct option is selected in all the drop-down menus.