Hi Delay Experts
I have a classic case of time being set at large in a delay claim in India.
I would have no problem promoting this in UK but nobody seems to have heard of the process in India.
I can also demonstrate that the situation is covered by the India Contract Act 1872.
Has anybody had any similar experience that they could share with me?
Best regards
Mike Testro
I agree the processes are slow in india. But it is more because due deligence is given there and there is multiple tyres for judgement.