HI, does anyone have any fixes which would allow me to create a link or constraint which would hold two tasks together so that wherever they were scheduled they would stay together, ie if task one is scheduled for monday and lasts one day task two must start on tuesday or vice versa if task two was scheduled for a tuesday task one must be scheduled for monday. The logical sequence is obviously there but when you resource level there is nothing to group them together. I know it sounds simple but it aint
Alex
unfortunately i need to relevel my resources regularly. thanks anyway
alex
Hi Alex
Use a single FS link between Task A and B.
Then set task A ALAP.
If you allow the software to level your resources then it will over ride any logic that you have previously set up.
That is why it should never be used.
Best regards
Mike Testro