When I exported project from p3,the resource type that assigned to the resources in P6 are not satisfactory,so I'd like to change the type of resources.
Is it possible by exporting to excel.
Thanks.
Hi all,
When I exported project from p3,the resource type that assigned to the resources in P6 are not satisfactory,so I'd like to change the type of resources.
Is it possible by exporting to excel.
Thanks.
Maybe the "Global Change" can changed the resource type.
Hi Ayman,
P3 does not knwo what a resource type is; therefore all your resources coming from a P3 project should be "labor"
if you have access to the resource sheet in P6 (you maybe should have admin rights to do so), it is easy to change the resource type, at least between "labor" and "nonlabor"; going to "material " is less easy
Alexandre