Hi there all,
I have a schedule prepared in MSP and I import it to P6 as an xml file. Durations of the tasks in the imported file appears in Original Duration column (as expected). However, when I change the duration of a task in the Original Duration column in P6, the bar in the Gannt Chart does not get longer or shorter. It gets longer or shorter when I change the duration in the Remaining Duration column.
The question I want to ask is, which column in P6 are the durations in MSP imported to? Is it Original Durations column or Remaining Durations column? or something else?
Thanks in advance.
I was interested in what the use of the option is. Good to know that during the import it gets shutoff.
You have a good day
Ron,
The thing is it was not me who has that specific checkbox turned off. When I import the xml file from MSP, it comes out to be unchecked by default. Since I was not aware of the function of the checkbox, I could not understand what was going on. Anyway, I solved the problem.
Sorry to take your invaluable time.
Regards,
Not sure why one would ever have this check box turned off. Does anyone know of a reason why this is an option, "Link Budget and At Completion for not started activities" checkbox under "Projects window => Calculations Tab
Not sure why one would ever have this check box turned off. Does anyone know of a reason why this is an option, "Link Budget and At Completion for not started activities" checkbox under "Projects window => Calculations Tab
I found the answer in one of the previous posts in forum. "Link Budget and At Completion for not started activities" checkbox under "Projects window => Calculations Tab" need to be checked. the problem is solved then.
regards to all