Default units/time change while importing

B
Babu PS 👤 Member for 14 years 11 months

Dear Firends,

We are working in Oil & Gas EPC Project in the Middle East.

We are facing a strange problem(!) with Primavera 6.0 Release 7.0.0.

When we imported a project it shows defaults units/time as 1/d for all labor resources. But when when the same file, exported to a release 6.0 version, it shows actual data set by our Sub contractor i.e., 8/d.

Please let me know how to fix this problem. We want actual data set by the Sub Contractor to be intact.

How to change the defaul setings as regard to resource defaults units/time -URGENT

A faster response will be sincerely appreciated.

Thanks in advance.

PS Babu, PMP

 

 

T
thaer ghanim 👤 Member for 14 years 8 months

hi

 

from( Menu bar ) choose (edit)..choose (user preference)..after that ( time units) choose( unit of time)..hour 

T
thaer ghanim 👤 Member for 14 years 8 months

hi

 

from( Menu bar ) choose (edit)..choose (user preference)..after that ( time units) choose( unit of time)..hour 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts