Guys,
I have developed a schedule in P 6.0, with resource loading. Following is the problem I am facing when viewing the Resource Usage Profile. The calender for both activities and resource selected is common 7 x 24 hrs.
I have say a resource mason with Defaults Units / Time : 8/d
Max Units / Time: 200/d ( ie 200 / 8 = 50 nos for the project duration)
Have assigned this to an activity PCC from 01.06.11 to 26.06.11 (25 days duration)
Now I want to allocate 8 masons for 25 days so have entered in Remaining Units / time : 64/d ( 8 * 8 ie 8 masons * 8 hrs / day for the entire 25 day durations)
But when I view in the Resource Usage Profile, I am able to view mason being allocated to only at the start of the activity and not being spreading all along the 25 day durations.
Rohit
Guys,
Thank you all for the help.[[wysiwyg_imageupload:692:]]Solved it. Here is the solution to it, select the period as per requirement but experts say to go for hours.
Rohit
HI
change the time scale to Days/week