Resource Usage Profile

R
Rohit K 👤 Member for 18 years 1 month

Guys,

I have developed a schedule in P 6.0, with resource loading. Following is the problem I am facing when viewing the Resource Usage Profile. The calender for both activities and resource selected is common 7 x 24 hrs.

I have say a resource mason with Defaults Units / Time : 8/d

Max Units / Time: 200/d ( ie 200 / 8 = 50 nos for the project duration)

Have assigned this to an activity PCC from 01.06.11 to 26.06.11 (25 days duration)

Now I want to allocate 8 masons for 25 days so have entered in Remaining Units / time : 64/d ( 8 * 8 ie 8 masons * 8 hrs / day for the entire 25 day durations)

But when I view in the Resource Usage Profile, I am able to view mason being allocated to only at the start of the activity and not being spreading all along the 25 day durations.

Rohitpm.jpg

R
Rohit K 👤 Member for 18 years 1 month

Guys,

Thank you all for the help.[[wysiwyg_imageupload:692:]]Solved it. Here is the solution to it, select the period as per requirement but experts say to go for hours.

Rohit

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts