P6 Rel 7 Lag

A
Ahmed KHR 👤 Member for 15 years 6 months

Dear planners;

When I run the update on P6 rel 7 , some activities don't start directly after the precedor one (See pic below)!

The lag on the relationship=0, and no Constraint.

Why I get this kind of probleme?

 

Image removed.

Regards,

T
thaer ghanim 👤 Member for 14 years 8 months

hi

 

Go to (Tool) from (Menu Bar),choose (Schedule ),Choose (Option),in General Tab ...down of the widow you can find

(Calender for schdeuling lag relation) --check what calender you are using in this option .

 

G
Gary Whitehead 👤 Member for 17 years 2 months

I can't see your picture, but this could be caused by:

-activty calendars

-other predecessors

-resource levelling

-resource calendars

-project calendars

-calendar shift patterns

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts