Productivity

Dear Friends

Letme know the productivity of Secant pile ..

Mike Iam  asking a rough idea.

regards

Arun

A
Arun Vasanth 👤 Member for 16 years 7 months

Thankyou mike

But please give me a rough idea for soft soil with 1 m dia 20 m depth..

Please

 

Regards

Arun

M
Mike Testro 👤 Member for 20 years 5 months

Hi Arun

It all depends on:

1. Size and depth of the pile

2: Type of rig ie Continuous Flight Auger

3: Number of rigs

First you have to drive the "Soft Pile" then the reinforced pile so you need two operations.

Do not forget the ring beam and then the temporary supports during excavation.

Ask your potential piling operator for precise details.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts