Dear All,
Our consultant commented the schedule,and sent us PDF files incorporating his ccomments in very short time.
I tried to take copy and past it herunder,but I don not know wich program /software he has used?
Can any body tell me?
SUCCESSORS REPORT
1 CPL.B1.Z1.04CO088 CPL.B1.Z1: STORE ROOM BLOCK WORK 24 30-May-10 23-Jun-10 28
CPL.B1.Z1.08CO919 CPL.B1.Z1:Pkg J.1 Store Room Door Installation 2 22-Sep-10 23-Sep-10 FS 0 12
CPL.AL.AL.01PM001 CPL.AL.AL: ZONE/SHOP READY FOR TENANT FITOUT (MILESTONE) 0 31-Jan-11 FS 0 0
2 CPL.B1.Z1.04CO089 CPL.B1.Z1: SERVICE CORRIDOR BLOCK WORK 18 30-May-10 17-Jun-10 28
CPL.AL.AL.01PM001 CPL.AL.AL: ZONE/SHOP READY FOR TENANT FITOUT (MILESTONE) 0 31-Jan-11 FS 0 0
CPL.B1.Z1.08CO915 CPL.B1.Z1:Pkg J.1 Service Corridor Door Installation 2 22-Sep-10 23-Sep-10 FS 0 12
3 CPL.B1.Z1.04CO091 CPL.B1.Z1: MALE WASH ROOM BLOCK WORK 30 30-May-10 29-Jun-10 28
CPL.AL.AL.01PM001 CPL.AL.AL: ZONE/SHOP READY FOR TENANT FITOUT (MILESTONE) 0 31-Jan-11 FS 0 0
CPL.B1.Z1.07CO950 CPL.B1.Z1: Pkg H Site Preparation 7 18-Jul-10 24-Jul-10 FS 0 162
CPL.B1.Z1.08CO926 CPL.B1.Z1:Pkg J.1 Male Wash Room Door Installation 2 29-Sep-10 30-Sep-10 FS 0 5
4 CPL.B1.Z1.31CO140 CPL.B1.Z1: BACK FILLING & COMPACTION 62 11-Mar-10 12-May-10 103
CPL.B2.Z1.15COA60 CPL.B2.Z1:Pkg G.1 Fix Reverse Osmosis Pipes From Borewell To Pumps 7 03-Sep-10 09-Sep-10 FS 0 53
EXT.AL.NO.15COA25 EXT.AL.NO:Pkg G.1: Drilling Bore Well 15 12-Jul-10 26-Jul-10 FS 0 43
EXT.AL.SO.15COA65 EXT.AL.SO:Pkg G.1:Drilling Bore Well 14 19-Jul-10 01-Aug-10 FS 0 50
5 CPL.B1.Z2.04CO088 CPL.B1.Z2: STORE ROOM BLOCK WORK 24 21-Apr-10 15-May-10 44
CPL.B1.Z2.08CO919 CPL.B1.Z2:Pkg J.1 Store Room Door Installation 2 22-Sep-10 23-Sep-10 FS 0 12
6 CPL.B1.Z2.04CO089 CPL.B1.Z2: SERVICE CORRIDOR BLOCK WORK 18 21-Apr-10 09-May-10 50
CPL.B1.Z2.08CO915 CPL.B1.Z2:Pkg J.1 Service Corridor Door Installation 2 22-Sep-10 23-Sep-10 FS 0 12
7 CPL.B1.Z2.04CO095 CPL.B1.Z2: LOW VOLTAGE BLOCK WORK 24 30-Apr-10 24-May-10 66
CPL.B1.Z2.08CO888 CPL.B1.Z2:Pkg J.1 Low Voltage Door Installation 2 22-Sep-10 23-Sep-10 FS 0 31
CPL.B1.Z2.07CO950 CPL.B1.Z2: Pkg H Site Preparation 7 25-Jul-10 31-Jul-10 FS 0 162
8 CPL.B1.Z2.04CO096 CPL.B1.Z2: HIGH TENSION ROOM BLOCK WORK 24 30-Apr-10 24-May-10 66
CPL.B1.Z2.07CO950 CPL.B1.Z2: Pkg H Site Preparation 7 25-Jul-10 31-Jul-10 FS 0 162
CPL.B1.Z2.08CO666 CPL.B1.Z2:Pkg J.1 High Tension Room Door Installation 2 22-Sep-10 23-Sep-10 FS 0 31
9 CPL.B1.Z2.04CO097 CPL.B1.Z2: TRANSFORMER ROOM BLOCK WORK 24 30-May-10 23-Jun-10 5
Thanks Justin,
I'll be appreciated if you can send me one of the available relevant softeware.
My e-mail is
use private message service
They might have used some schedule analysis softwares like Pertmaster or Monto carlo and many more softwares are available now
Thank you Justin for your reply.
I'd like to ask which siftware the consultant used to get that report.
because it is not primavera 6 report.
Could not understand your question..please explain clerarly.