Micro tunneling

Dear Friends

As every body knows I am in  a STP Project .

I have started working on the Program,Tommorow Iam Startting to Schedule the Microtunneling portion.

I am little bit confused in some areas relating the sequence.

So any body have STP experience please guide me from the Shaft onwarsd..

I am showing the activities by sequence ,If any correction is there please correct it..

1,Secant piling

2.Excavation & Ring beam installation

3.Temporary blinding for jacking

4.Base slab Concreting

5.Thrust wall

6.Microtunneling

7.Manhole Installation

Please help,,,,,,

M
Mike Testro 👤 Member for 20 years 5 months

Hi Arun

I have to admit that I am getting a bit fed up with this exchange.

It seems that you know nothing about HDD Boring.

If my advice is not clear enough then ask one of the engineers on your project who knows what to do.

End of conversation

Mike Testro

A
Arun Vasanth 👤 Member for 16 years 7 months

Thank you mike

 

Please breif me about Thrust wall ..

Base slab is after Microtunneling or before ...

M
Mike Testro 👤 Member for 20 years 5 months

Hi Arun

You have the correct sequence for each drive - just put a FS link between each task and summarise for each drive..

It must be deep if you need a piled header - if it is not a permanent structure then temporary steel sheet piles would be quicker and cheaper.

Bore Lining and Hyrdotesting will  come between drilling and manholes.

Best regards

Mike Testro

A
Arun Vasanth 👤 Member for 16 years 7 months

Yes it is mike

 

Mike please help me to make the sequence...

 

Regards

Arun

M
Mike Testro 👤 Member for 20 years 5 months

Hi Arun

You seem to have got it about right.

Is it HDD boring?

Is there any hydrotesting?

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts