Planned% percentage Complete

S
Sajid Syed 👤 Member for 18 years 4 months

Hi,

can some one comment on how to display  "Baseline % Complete" for activities as well as being summed up for the WBS levels as well.

the project is currently 50% into progress and "scheduled % complete"  values are not the same as the ones that i had initially calculated for the scurve from baseline.

Schedule%complete gives rescheduled values not the baseline values as i understand????

 

 

Regards

 