Dear planners,
I have a strange situation.i am using ms project 2007.the problem is milestone tasks not displaying 0d and % complete.this is happening for few activites only.when i add new activities they are showing the 0d and %complete.
Any help
urgent
Thanks
kp
I use 2003, but i assume this will be the same as 2007.
If you go to the task information box for this "milestone", under advanced tab there is a check-box called "Mark task as milestone"
If this is checked, the task will appear as a milestone on the gant chart even though it has a duration, % complete, resources, etc
To correct, you can choose to either uncehck this ox and treat the task as an activity, or set the duratino to zero and treat it like a milestone.
I have never understood why MS Project allows for this functionality. It seems quite peverse.