updating hammock task in MSP 2007

K
kp rao 👤 Member for 15 years

Dear planners,

I am using MSP 2007.Hammock activity is not updating itself.How to set auto update of hammock task.It is like update the tasks and hammock task will be updated.

urgent help

Regards,

kp

N
Niek Zonneveld 👤 Member for 21 years 4 months

kp,

You can do this but it is not straightforward.

You can copy a cell in MSP and then paste the content as a link into another cell (through paste special, paste link)

Just copying a date into the destination cell won't work because that will normally just impose a constraint and not change the duration.

Cleaver use of formula's in combination with the above links will probably get you there, but remember MSP gets 'nervous' from these links as it keeps recalculating/updating continuously.

H.T.H.

Featured Partner

Top Posters

jeoffrey reyes
15 posts
Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts