Dear Friends ..
I am facing a problem in P7. I prepared base program and updated.while updating the program the orginal durations in
different WBS Levels are different .Is there any solution .Please help
Regards
Arun
Dear Friends ..
I am facing a problem in P7. I prepared base program and updated.while updating the program the orginal durations in
different WBS Levels are different .Is there any solution .Please help
Regards
Arun
Hai Artagnan
I updated Program Manually..
Regards
Arun
Arun,
How did you update the program? Manually or some external application such as excel or SDK?
Arun,
How did you update the program? Manually or some external application such as excel or SDK?
Maybe it is because WBS duration is a calculated value (*) and not a fixed entry is why it behaves in this way.
I can think of two workarounds.
Use global change and store original duration as a user defined field, in this way it will be frozen at the activity level as well as at the WBS level, verify on this as I am not a P6 user, I am applying what I recall from my previous use of P3e, P3 and SureTrak.
Store your initial job as a baseline and on updates display baseline original duration next to current schedule original duration.
Hope this helps.
Hai Friends
Any experts to answer my above question????
regards
Arun