I joined as a planner in a water pumping station project . My first task was to
revise the delayed base program with out changein the Project finish dates.
I changed some relations of the activities and I have completed that task.
Now my real problem starts here.I dont want to delete the completed activities.
The same actual dates I want to show as planned dates in my revised program.My intension is to show the planned bar and Acyual bar in same time.
Dear Experts please help me in this issue ...
Regards
Arun .V
Thanks
Jash & Friedieee...
Thanks for the back-up comment Sir Ferdie.
hi arun
Jash already explained it, adjust the settings in admin menu
remove your baseline first in maintain baseline, then create your baseline again in maintain baseline using your current project
after assigning it, everything will be ok
As I have said in my previous comments, you can use your updated programme as your revised baseline if your client approve it. modifying your baseline dates means you're revising it. why you dont just show your real delay in that particular activity; besides, your completion date in your updated programme is same as your baseline.
Thank you Jash
Jash I have revised the old updated program RV00.
As every body knows there wont be change in the Actual dates ..
Eg.. In ActivityID 1000 baseline start and finish is
10-10-2011 and 30 -10-2011 respectivley.But actual dates are 10-11-2011 and 30 -11-2011.
In revesion 01 program I want 10-11-2011 and 30 -11-2011 as base program start date which is equal to Actual start.Is there any solution????
In the revised updated program I want the actual dates and Baseline line dates be same .....
Hi Arun,
In your case, you are revising your original baseline by reflecting your current actual dates and revised relationship of unfinished activities to recover your delay and this will need the approval from your client.
First, get an approval from your client and once you have it you can convert and assign ur updated schedule into baseline.
Now, your question is, you want to show your planned bar similar to your actual bar? after you assinged your updated schedule as your new baseline, go to admin windows, click admin preference and go to earned value; choose earned value calculation as "Budgeted values with current Dates".
Gudluck,
Jash
Dear Mike
Thank you for your reply.
Aftr long time u r replying my Qurery
But I didnt get you...
Could u guide me through commends in Primavera P6 for same autal dates as base dates..
Regards
Arun V
Hi Arun
Set up a baseline / target programme that will underlay the live programme.
Best regards
Mike T.