Progress Measurement System for EPC project

Appreciate your expert opinion on this...

For an EPC project, we have a master schedule with 3 phases of work; engineering, procurement and construction.

In our project, construction portion is using quantities as the basis for progress measurement, engineering is using the total deliverables/drawings in getting the percent complete while procurement is based on delivery of equipment/materials.

In other words, each phase has different basis of measurement. The 3 phases of work is joined together in one master schedule.

Question: What progress measurement to use in the master schedule?

 

Edwin

G
Gary Whitehead 👤 Member for 17 years 3 months

Cost or manhours are typically used as a common unit of measure for performance across the 3 EPC phases. Often cost is chosen so you can use the schedule to forecast future costs & cashflow. Whereas use of manhours is arguably a better measure to weight work done.

NB: Be sure everyone agrees in advance of how you do this, because there are a number of ways of splitting the weightage.

eg: if using manhours, do you use just direct manhours, or include subby manhours? or management time?

if using cost, when is the cost of expensive procurement items claimed? on delivery? installation? commissioning? a portion claimed at each?

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts