P6 - Additional 1 day duration

In the programme I'm working using P6, I'm using "day" as the unit of time. I set Admin Preferences>Time periods to 24 Hours/Day. I did the same for the calendar. But for an activity with a 1 day duration, which will start on 08-Aug-11 00:00, it will be finished on 09-Aug-11 00:00. Actually it is the same for every activity of any duration. So if I will not show the time, if you look at the start and finis date, it is like having an additional 1-day for the duration. Anybody knows how to fixed this? I read some previous thread but I haven't found any solution. Thanks.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Ronn

It is like a fence - the dates are the fence posts and the gaps is the duration - there is always 1 more fence post than gaps.

Maybe you can set your duration to 1 second before midnight - you can in Asta Powerproject.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts