Show Remaining Units by Shift for all Resources

I am having trouble getting the Planned or Remaining Units by Shift into an Excel file. I think I figured out a way using the Resource Usage Spreadsheet but I can't get all the resources to show up all at once. Is there a way to allow you to view planned units by shift with every active project resource. I can just copy each resource one at a time but I would rather do them all at once. P3 was very easy to extract this data and I am having a little trouble doing the same thing in P6.7. This information would be used for an S-curve in Excel. Any help Would be greatly appriciated.

 

Thanks,

Josh

J
Josh Roberts 👤 Member for 14 years 10 months

I think I might have figured it out. I ran a Resource report using Resource name and adjusted the timescale accordingly.  If you don't mind, could you send me your format anyway so I can see if it might be diffrent? [email protected]

 

Thanks in advance,

Josh

M
Mike Testro 👤 Member for 20 years 5 months

Hi Kumar

You can use the PP private message service.

Best regards

Mike Testro

K
kumar s 👤 Member for 16 years 4 months

Dear Josh,

 

You can get the loading of  Planned or Remaining Units shift wise by report.

I have a report format where you will get the loading shft wise.

send me your mail id i will forward it.

 

Cheers

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts