Hi guys!
Just want to seek any advice/solution on my problem regarding Budgeted Cost in P3.
I got a cost loaded program. It has Budgeted Costs however, when i checked the Data for Resources, I noticed that the Price/Unit for each Resource is 0. This is very odd because there is total cost for each activity but the price/unit of any resources it has is 0. This Budgeted Cost which I have displayed is not a Custom Data, as I checked.
Any same experience I am having? Please advise.
Thanks,
Ariel
Guys,
It is in the COST Tab in the activity form. It is a DIRECT INPUT that is why it has cost although the resource assignment has no price/unit or budgeted quantity.
Best regards,
Ariel
Hi Faiz!
Thank for your reply, Is P3 has EXPENSE tab? I think it has not & can't find it, only in P6 & higher versions...
Thanks,
Ariel
Hello Ariel,
The Cost you are seeing is may be the Expense Cost loaded Directly in The Expense Tab.
Regards,
Faiz
Here is the screen shot of what I am saying, really this is very strange...How is these Budgeted Cost calculated by the P3 if Price/Unit is 0???...I used to input budgeted cost by assigning a resource with 1 as "Price/Unit" and the cost as the "Budgeted Quantity" to minimize the my Resources.