I have a schedule, with 1700 WBS Codes.
Within each WBS Code I have 5-20 activities.
I would like the total float to be driven from a certain activity within each WBS Code.
So basically every WBS acts as it's own entity.
Right now, all Total Float is driven from the Latest Finish Date of the entire schedule.
Is this possible?
If yes, please give me a hint :)
Total Float - Is it possible to change the driver to within a WBS Code?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Rock on Paul Harris!!!! Thank you very much!!
In the Tools, Schedule, Options, select "Make open ended activities critical" and all activities without successors will calculate their own critical path.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.eastwoodharris.com
www.primavera.com.au- a Primavera scheduling software resources site
Dear Jones,
I think that's the only way........................
Well, I've found out there is no way to globally change the driver for Total Float to per WBS.
What I need to do is set my last activity in each WBS to Mandatory Finish.