The issue is not saving the PP to Primavera format its what happens when you open in P3 or P6.
Avoid use of multiple tasks on bars, each task in PP will become an activity in P3/6
I can only suggest that prior to saving your PP file to an XER format you open your PP file in a table showing the unique task ID (task per line option). Copy the Unique task IDs into excel, in excel change the UID's to consecutive numbers then copy and paste back into PP.
Now save file as xer. You may still have some schedulling issues but at least you can sort the activities into the same order in which they were in your PP file.
There is this job i'm chasing and that's precisely what they want my to doooooo.... I don't know whyyyyy.. They need me to convert from PP to P6 and do some presentations....... Funny isn't it
I've had recent cause to import a file generated in PP into P6. Most of the data imported OK including activity codes and calendars. However, the devil is in the detail. There were some errors in the transfer process leading to incorrect scheduling of some activities. Grouping and sorting also required a bit of work. It is certainly not a painless process but with a bit of work shouldn't cause you too much trouble.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Geoffrey,
I was faced with this problem once before.
The issue is not saving the PP to Primavera format its what happens when you open in P3 or P6.
Avoid use of multiple tasks on bars, each task in PP will become an activity in P3/6
I can only suggest that prior to saving your PP file to an XER format you open your PP file in a table showing the unique task ID (task per line option). Copy the Unique task IDs into excel, in excel change the UID's to consecutive numbers then copy and paste back into PP.
Now save file as xer. You may still have some schedulling issues but at least you can sort the activities into the same order in which they were in your PP file.
Barry thanks for your recommendation
Mike Thanks,
There is this job i'm chasing and that's precisely what they want my to doooooo.... I don't know whyyyyy.. They need me to convert from PP to P6 and do some presentations....... Funny isn't it
Hi Geoffrey,
See the attached link
http://www.eh.com.au/Technical%20Papers/070728%20PowerProject%20&%20P5%20Import%20and%20Export.pdf
I've had recent cause to import a file generated in PP into P6. Most of the data imported OK including activity codes and calendars. However, the devil is in the detail. There were some errors in the transfer process leading to incorrect scheduling of some activities. Grouping and sorting also required a bit of work. It is certainly not a painless process but with a bit of work shouldn't cause you too much trouble.
Regards,
Barry
Hi Geoffrey
If you have Powerprfoject v 10 or 11 and P3 on the same drive you can convert directly between the two systems.
P3 can then be upgraded to P6.
You will howver lose a lot of detail from PP.
You may try saving PP as an .xml file but I do not know if P6 will accept it.
The thing that I really want to know is - Why bother?
Best regards
Mike Testro