Resource Assignments - Manual Entry of Costs

Hello All,

 

I'm having trouble understanding resourcing/resource assignments. Every which way I turn I can't seem to find a place to manually enter a cost per period of an activity. I don't want to base it on a rate, and so enter man-hours to multiple that rate, I simply want to say activity A has a cost of X during week 1 and cost Y during week 4 etc etc.

 

Any help would be much appreciated thanks.

 

Chris

S
Syed Abrar 👤 Member for 18 years

Hi Chris,

    for each activity you can define a curve. pls see below how to create a new curve inaddition to default ones as u required

[[wysiwyg_imageupload:600:]]

I hope ur query is answered,

 

Syed Abrar