Loading resources in Microsoft Project

M
Miguel Rios 👤 Member for 16 years 9 months
S
shola ojo 👤 Member for 15 years 7 months

Trevor,

After you resource load, How do you populate the manhour graph by either "tasks" or "roles". Please advise?

R
Rohit K 👤 Member for 18 years 2 months

Hi

If I have to allocate a gang of 75 carpenters for the entire project, should I enter 7500% in the max units column in the resource sheet and later as per the quantum of work in the task and duration I enter the required carpenters for them?

Is this correct?

 

Rohit

T
Trevor Rabey 👤 Member for 20 years 8 months

There are several ways, some of which are not recommended.

This one is good:

Go to the Resource Sheet View and create and define them first.

Then go to the Gantt Chart View, select a task and use the assign resources icon/button on the toolbar to show the Assign Resources dialog... etc.

Featured Partner

Top Posters

jeoffrey reyes
15 posts
Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts