Good evening guys,

I have got one question i have scheduled one project in picrosoft project.

start date is : 18.07.2011

End date is 30.08.2011

Relation :FS

i have entered status date as 28.07.2011 and i dint updated any tasks, then i enetred F9 to caleculate mannually , i am not able to see any negative slack of 10 days (or delay of 10 days since i dint started any work) 

if any one has answer please let me know. thanks in advance please note i have tried with must finish contraint too but the resilt is zero

 

 

R
Rafael Davila 👤 Member for 22 years 4 months

Make sure you set a must finish project date constraint if you want to compute float relative to such date. It can create negative float or even a longest path with positive float.

If you do not set a finish date constraint no negative float will be computed and float will be zero along longest path.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts