Hi Jash
There is no need to reply to a thread that is more than 5 years old.
Best regards
Mike Testro
Hi Shengyun,
External dates exists only when your activity is link to another activity in different project; therefore, it cannot be filled directly in the column of your current programme. These dates indicates only when your activity is link externally to other project.
Regards,
jacob
what i trying to say is i can not fill the column of external early start data also the external early finish data. i double kick the blank of this column, it will display a dialog box of calendar,u can choose any day there,but after that,its still blank there.its seams we can not fill this column by manual work.
Q1,in which case this column will have a value?(whatever by manual work or by calculated.
Q2,in which case i have to use this external early star data?
Q3,how to use it?
Thx~
Best Regard~
Sandwind He
Hi,
What do you mean by external early start and finish.
Regards
Dinesh