if the activities used more than calendar how p6 calculate the variance finish or start for grouping band
Grouping band
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Durations and, I assume variances also, of grouping bands are calculated using :
The below links to a presentation by Paul Harris which covers this and other common issues:
http://www.eh.com.au/Technical%20Papers/100602_P6V_%20Bars_Tricks_and_Traps.pdf
Hi Raed
As far as I am aware only one calendar can be assigned to a task.
Different calendars can be assigned to resources allocated to the task - in which case chaos reigns.
Best regards
Mike Testro