Hi,
You can understand the difference by reading this post https://doduykhuong.com/2016/09/06/how-to-update-baseline-in-primavera-…
Select the activity
Select the "Status" tab
tick the "Started" box
choose the correct "started" date
tick the "finished" box
choose the correct "finished" date
Can you help me? I need to update from 0% to 100 %.
How can I update the % complete from 0% to 100 %?
Restore baseline detatches the baseline from the project and restores it as a project. Update baseline updates any changes that have been made to the main project into the selected baseline.