a) How to  remove complete progress instantly from the whole programme containing 1000  activties ? any tip  please share.

b) How to remove links completely and instantly given to 1000  activties from the whole programme  ? Please tell me the steps.

 

Experts please reply above...

G
Gary Whitehead 👤 Member for 17 years 2 months

a) Use the global change tool.

Global change can be very dangerous if you don't know what you are doing, so take a copy of your project before attempting.

To remove all progress completely, I THINK (you will have to confirm by trial & error) you will need to set the rules like this:

"If activity status does not equal Not Started, then make activity status equal Not Started"

Do a trial run before making the change.

 

b)

1) Got to Enterprise, projects.

2) Select yuor project and copy

3) Paste it in same area. You will be given options as to what to copy. Select everything except "relationships"

A
Amit Parmar (PMP) 👤 Member for 15 years 6 months

Hi Jeremy,

1)Make a new project and open you current and new project together. Copy the TOp node of WBS from your current project into the new project. You will get different option when you do that. Uncheck  the option Copy Relationships. Only activities will be copied to the new project and relationships will be left behind. STart working on the new projectt as usual.

2) To remove actuals, use global change as use the options in the image below. Use all the conditions mentioned properly

[[wysiwyg_imageupload:565:]]

Regards

Amit Parmar

Check out my blog on Primavera at http://www.primaverablog.in

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts