Well if you are using wbs to summarise, mukunda has it right: Just go to project, wbs and you can change the heirachy, sequence, and colour scheme of the elements.
If instead you are summarising using one or more activity codes, you can do the same from enterprise, activity codes
In Asta, when you move summary bar, every thing moves underneath but P6 is completely **** software.......P6 is taking too much time in doing such things while Asta is time saving software.
Why companies like P6 is totally after thought? isnt?
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Thu, 2011-06-30 13:43
Member for
16 years 7 monthsOh I see. Well if you are
Oh I see.
Well if you are using wbs to summarise, mukunda has it right: Just go to project, wbs and you can change the heirachy, sequence, and colour scheme of the elements.
If instead you are summarising using one or more activity codes, you can do the same from enterprise, activity codes
Member for
19 years 10 monthsHi Gary I think Jeremy is
Hi Gary
I think Jeremy is talkning about moving summary bars up and/or down within the heirarchy not laterally along the date line.
In Asta you just drag and drop on the screen - how do you do it in P6?
Best regards
Mike Testro
Member for
16 years 11 monthsProject>Wbs here u can change
Project>Wbs here u can change the summary tasks to the required format,
Member for
16 years 7 monthsI'd advise you to spend some
I'd advise you to spend some time learning the software before deciding it is completely ****.
I find P6 easier to use than Asta, but that's just because I know it better.
Member for
14 years 4 monthsThanks Gary.In Asta, when you
Thanks Gary.
In Asta, when you move summary bar, every thing moves underneath but P6 is completely **** software.......P6 is taking too much time in doing such things while Asta is time saving software.
Why companies like P6 is totally after thought? isnt?
Member for
16 years 7 monthsThe summary bars summarises
The summary bars summarises the activities below it.
If you want to move the summary bars to different dates, move the activities they are summarising to different dates, and the summary bar will follow.