Current Project set as baseline shows different dates

Hi,

 

in P6 I set the current project as primary and project baseline. In the bar chart view some start and finish dates are different. Anybody can help?

 

cheers

M
mukunda y 👤 Member for 17 years 6 months

As Ronald said Concept of Baseline Start & FInish, Start & finish dates are different.. I advise you to understand the conecpt of these dates

R
Ronald Winter 👤 Member for 23 years 5 months

Eckart,

 

When used as a Baseline, the schedule will show Planned Dates, which is sometimes different from Start Dates.  Good Luck!

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts