Not transparent behavior of scheduler

M
Maciej G 👤 Member for 15 years

 

I have set two tasks in automatic mode: one task after another using predecessors link as defined below. Task A is completed in 100%. 

Id |Task Name |Predecessors|Start|Finish265|Task A|264|Fri 24/06/11|Mon 27/06/11266|Task B|265|Fri 29/07/11|Thu 04/08/11

What I don't understand is why MS Project schedules Task B a month after the first one. I'm particularly missing feedback from MS Project justifying this decision. Without this feedback nailing down the problem and its reason becomes hard.

  1. What could be the possible reason for that?
  2. How can I get feedback from MS Project with explanation why the given task has been scheduled in a certain way?

Some more details here:

  1. Task B contrain type is "Start as soon as possible"
  2. Resources assigned to the task have no holidays in this period (no exceptions in calendar)

Thank you in advance,

Maciej

M
Mike Testro 👤 Member for 20 years 7 months

Hi Maciej

What was the date of your progress report where you set task A at 100%?

Best regards

Mike Testro

Featured Partner

Top Posters

jeoffrey reyes
15 posts
Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts