Global Change for Calendars

What criteria need to set up in Global Change to change the Calendar from 7 weeks to 5 weeks which may change calendar of all actvities?

Thanks

R
Ranjit Kumar Kumar 👤 Member for 16 years 8 months

Hi Jeremy Simth,

Select Enterprise > Calendar > Add > Select any Calendar from the existing calendar > Modify > Work week > Which day you want to off put 0 or other wise put all 8 hours then it will change from 5 work days to 7 work days > Click on the Default.

 

Assigning the 7 days work week to all the activities.

View > Columns > Click on the General and find out the Calendar > Ok

 

Change the existing calendar by the new calendar in one cell.

After wards click on the new cell (new calendar cell) then use the command shift and select all the activities > go to the Edit > fill cell.

I hope it will work

Thanks and regards,

Ranjit

S
Shah. HB 👤 Member for 17 years 6 months

Hi Jeremy Smith

1. Create a calendar of 5 Weeks 

2.Filter the activities you need change (If any )

3.Use file down option to replace 7 weeks to 5 weeks

///Is it weeks or days?///

Regards

Shahul

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts