I am using P6 Ver 7.0. Can any body tell me how to bring planned value histogram in resource uage profile.I able to get budgeted Histogram but not planned histogram.
Thanks.
I am using P6 Ver 7.0. Can any body tell me how to bring planned value histogram in resource uage profile.I able to get budgeted Histogram but not planned histogram.
Thanks.
use activity usage profile
baseline tick box is there
Akhtar,
Budgeted is the same as Plan