Microsoft Project Member for 16 years 10 months Member for 16 years 10 months Submitted by Amro Ahmed on Thu, 2011-06-23 03:26 Permalink i know how enter these data i know how enter these data but after finishing update some actual dates will be before data date cause it not work in retained logic just dates. my question if there is a solution for this issue. Member for 14 years 9 months Member for 14 years 9 months Submitted by EllenPMP on Wed, 2011-06-22 17:54 Permalink From the Gantt chart show the From the Gantt chart show the tracking table. You will be able to enter in actual start and finish dates for a task. Log in or register to post comments
Member for 16 years 10 months Member for 16 years 10 months Submitted by Amro Ahmed on Thu, 2011-06-23 03:26 Permalink i know how enter these data i know how enter these data but after finishing update some actual dates will be before data date cause it not work in retained logic just dates. my question if there is a solution for this issue.
Member for 14 years 9 months Member for 14 years 9 months Submitted by EllenPMP on Wed, 2011-06-22 17:54 Permalink From the Gantt chart show the From the Gantt chart show the tracking table. You will be able to enter in actual start and finish dates for a task.
Member for
16 years 10 monthsi know how enter these data
i know how enter these data but after finishing update some actual dates will be before data date cause it not work in retained logic just dates.
my question if there is a solution for this issue.
Member for
14 years 9 monthsFrom the Gantt chart show the
From the Gantt chart show the tracking table. You will be able to enter in actual start and finish dates for a task.