Holding an Activity

A
AB Timo 👤 Member for 14 years 11 months

Hi,

I am Faiz.have been working for last two years as Planning Engineer Using Primavera V6.

I needed to ask that when I want show a activity on hold how to show it precisely.I tell you my procedure and you tell me that wither it is right or not??

I have an activity named "Mobilization"

The Planned Start is was 11th june 2011..and it started on the planned date i.e, 11th june 2011,

But it was holded due to some reason on 15th june and will remain holded till 18th june.

So I Started the activity..then entered the date of suspension and also the date of resumption.

is it Right??????But in bar chart it delays the activity not showing any different color for the suspended period...how to show it in the bar chart or activity table???

 

regards,

G
Gary Whitehead 👤 Member for 17 years 2 months

You are using the correct procedure.

To show it in the bar chart:

1) right-click on bar chart area, select bars

2) select the relevant bars (eg actual work & remaining) and go to Bar Settings tab

3) Ensure Bar Necking for Activity Nonwork Intervals option is ticked

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts