Types of schedules

J
John Power 👤 Member for 16 years 2 months

Hello all

M
Mike Testro 👤 Member for 20 years 5 months

Hi John

Basically the evolution of a construction programme goes something like this:

1.  Tender Programme - should be at level 4 but rarely is.

2.  Contract Programme - A development of the Tender programme - after award - based on the best information available - must be at level 4 - Sometimes called the Baseline Programme - submitted for approval

3.  Revised Programme - Prepared when there are any changes in the scope of work or any delay events - the baseline saved in a new file name - often results in an EoT situation.

4.  If the Revised Programme is approved it then becomes the new Baseline - numbered sequentially 01 > 02 etc.

5.  A Mitigation programme is where the original logic in a revised programme is changed to reduce the end date at no extra cost to the contractor.

6.  An Acceleration programme is where the overall duration is reduced with extra cost - this is very difficult to get right and should only be done after mitigation.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts