Planning Unit in P6

Hello, please what determins what planning unit to use when you are creating a schedule (hr, day or month).

Cheers

kay

M
Manoj VS 👤 Member for 16 years 11 months

Hai Bobo Kay,

My suggestion is Planning unit depends on requirement of the project / activities of the project. Project like shutdowns which require monitoring hourly basis planning unit is hr,  and for projects for which hourly basis monitoring not required day can be planning unit.

Regards