Setting Resource start and finish to equal activity start and finish

Member for

19 years 1 month

still unclear, how about restoring your baseline?

have you levelled your resources manually or automatically? - I believe Rafael is the expert on this one.

are you using different calendars? how many?

For example: You use different calendars for activities and resources; and then you level your resources automatically, what happens? or what is the result?

Member for

17 years 11 months

For clarification the situation is this:

In the past for various reasons the start and/or finish dates of resources assigned to activities have been modified manually so that in many cases the dates do not match the activity start and finish dates.

I am looking for a quick way to revert all assigned resources on the programme back to the original default dates which match the activity dates when the resource is assigned.

Thanks,

Nathan

Member for

19 years 1 month

I'm not sure if I understand you correctly, but how about using exactly the same calendars for both activities and resources?