Custom Field Formula in P6
Forum Sponsor
Top Posters
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
In primavera you have can do it through Global Change, select the custom filed and you can assign the formula. Unlike in MS Project, here you have to run Global change every you want to have the custom field updated. i.e. when ever you update the actual work you should also run the global change to reflect the updates into the custom field.
if we use physical % not u % and we just wanna the calculate A.M formula what should we do?
Antonio
Sorry, your last sentence I dont understand.
In Primavera you have many possibilities for %-complete. Study this part within the reference manual or activate the "Hint Help". There you find the formula each field is calculated.
Units %-complete is calculated the way you described.
Regards
Dieter
Dieter, thanks for u reply.
Ok. this field (Units %-complete) show the Real % based on unit. However, i need show the weight of WBS. Ive to calculate: ( budgeted unit / total budgeted unit (in MS Project i input it manually))*100.
I need to know about the activity in terms of working on the project.
Antonio
"The percent complete of units for all labor and nonlabor resources assigned to the activity. Computed as Actual Units / At Completion Units * 100. Always in the range 0 to 100."
This was taken from the "Hint Help" for "Units %-complete. No need for a UDF.
Regards
Dieter