Does anyone know how to display week numbers for the duration of a project along the timescale in Powerproject?
The drop down menu does not give it as an option?
Does anyone know how to display week numbers for the duration of a project along the timescale in Powerproject?
The drop down menu does not give it as an option?
Hi Lee
Read what Chris told you and set the start date to zero at week 1.
It also helps if you set the same start date in File > properties.
Best regards
Mike T.
Many thanks for your replys.
It seems to show Week No. 1 as -1? and if you change it to the week before the print preview shows starting on Week No.2?
Has anyone encountered this?
Lee
Mike is correct about the elapsed unit but if you need to change the week 1 position, right click in the date zone and go to Properties. Go to the Date/Scale tab and change the date zero date to where you want week 1 to start from.
Chris
Hi Lee
Right click the date zone - click Insert Line - select Elapsed Units
Move the line up or down to the required postion.
Best regards
Mike Testro