How to Display Week Numbers

L
Lee Mallek 👤 Member for 21 years 1 month

Does anyone know how to display week numbers for the duration of a project along the timescale in Powerproject?

The drop down menu does not give it as an option?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Lee

Read what Chris told you and set the start date to zero at week 1.

It also helps if you set the same start date in File > properties.

Best regards

Mike T.

L
Lee Mallek 👤 Member for 21 years 1 month

Many thanks for your replys.

It seems to show Week No. 1 as -1? and if you change it to the week before the print preview shows starting on Week No.2?

Has anyone encountered this?

C
Chris Rymer 👤 Member for 15 years 11 months

Lee

Mike is correct about the elapsed unit but if you need to change the week 1 position, right click in the date zone and go to Properties. Go to the Date/Scale tab and change the date zero date to where you want week 1 to start from.

 

Chris 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Lee

Right click the date zone - click Insert Line - select Elapsed Units

Move the line up or down to the required postion.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts