Primavera Calendar P6

I have some problem...

In the same  project ,Activity "A" can be carried out only day shift ( 8 hrs), and Activity "B" to be carried out day and night shift ( 24hours).

 

Please let me know how to assign the different calendar for the same project in Primavera P6

 

Senthuran

M
Mike Testro 👤 Member for 20 years 5 months

Hi Muthukumaru

Another point to remember is that different calendars will affect the critical path - for instance:

If your 24hr task ends in the middle of a hoilday period and is linked to an 8hr task that starts after the holiday the gap will register as float.

Best regards

Mike Testro

G
Gary Whitehead 👤 Member for 17 years 2 months

To create or ammend different calendars, go to Enterpise > Calendars

 

Assigning a calendar to a particular activity can be done in the general tab of the activity details window

 

NB: When using different calendars on a project, it is important to understand which calendar will be used when calculating lags. To do this, got to tools > schedule > options.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts