Loading Budgets , Earned Value

Guys , please we want to implement a simple Earned Value system here, I want to take budgets from the BOQ and load it at a WBS level and not at an activity level we want to measure our Earned Value at this level , However how or where does one input these values into P6

N
niles luo 👤 Member for 20 years 6 months

Hi,

    maybe you can do as the following steps.

    Create an WBS type activity for each WBS that you want to Calculate the Earned Value

     Each WBS type activities' progress should be set as physical. 

     Load budget for each WBS type activity, then save as baseline.

    Each datadate, the cost and progress should be updated for each WBS type activity.

    If you have done the above step, you could do the EVA

Good luck

G
Gary Whitehead 👤 Member for 17 years 2 months

Your best bet is probably to create a summary LOE task per wbs element you want to load, and link it to all activities within that element.

 

You'll have to think carefully about how you measure progress, though.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts