Hi All,
I have a difficult situation here. Need help.
I am preparing a Baseline Schedule.
1) I have set up resource dictionary with Price/Unit, Units/Time and all other required data for each and every resources.
2) Then, I have assigned these resources to a particular activity. Say activity A.
3) Now, in the activity details -> Resource tab, I am not able to see Price/Unit & Budgetted Cost.
Why? Did I miss anything here?
Please helpout.
Thanks in advance.